The process of modular construction from design to completion
Contents |
[edit] Introduction
Even though off-site construction is generally a more simple process than traditional building, there can still be advantages to using a company which can support every step of the process. Turnkey services offer expert guidance from the first meeting to the last coat of paint.
[edit] Devising the concept and design
The first step in any project is determining what the customer wants. When choosing off-site construction, several factors can influence this decision. How many rooms are required? How high will the structure go – single storey or multiple floors? Where will the building be located?
Time should be taken to discuss these questions with customers and run through the options in initial meetings so that they can be certain that they have covered all the angles. From there, the plans can be put together and a quotation provided.
Customers should be kept informed throughout the process, and the use of building information modelling (BIM) allows customers to see what the finished product will look like before manufacturing begins.
The added advantage of this approach is that the final cost should not differ from the initial quote, helping customers to plan and control their expenditure.
[edit] Managing the planning process
A question asked repeatedly is whether or not planning permission and building regulations still apply to modular buildings. The answer is yes.
The first step is to liaise with the council’s planning officer and manage the full process, including submitting the plans in the correct format and ensuring they are complete.
From there, the next step is the building regulations application, which covers the functionality and structural performance of the building to ensure that it complies fully with requirements. The regulations look at the robustness and safety of the finished building as well as taking account of fire safety, drainage, potential for contamination, ventilation and so on.
[edit] Construction and installation run concurrently
Once planning permission is secured from the local authority, groundworks can begin on-site. Skilled tradespeople will dig foundations and liaise with utilities providers to ensure that all services connections are in place so that the final structure can be easily dropped into place.
The construction works begin at the same time in a specialist factory, where the building is assembled ready to be installed on-site. The final step in the process is dropping the finished building into place and connecting the utilities. Exterior cladding (which starts in the factory) is finished off on-site, as is plastering and painting.
[edit] How long is the modular construction process?
Using a company that can manage the design and construction process from start to finish is the most efficient way to ensure that a project is completed in a timely manner.
After the initial discussion, the quick generation of plans and a quotation puts the customer in position to start the planning process. This is where delays can occur: securing planning permission and building regulations approval can take anything from six weeks to three months depending on the local authority, so taking advantage of an experienced team which is well-versed in the process can be worthwhile.
The rest of the process can be relatively simple: the groundworks will run alongside the factory build, so within four to six weeks the structure will be ready to installed. As the time on site should take just a couple of weeks, the whole process can take no more than three or four months.
Featured articles and news
Homes, landlords. tenants and the new housing standards
What will it all mean?
The Architectural Technology podcast: Where it's AT
Catch-up on the latest episodes.
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.
Level 6 Design, Construction and Management BSc
CIOB launches first-ever degree programme to develop the next generation of construction leaders.
Open for business as of April, with its 2026 prospectus and new pipeline of housing schemes.
The operational value of workforce health
Keeping projects moving. Incorporating unplanned absence and the importance of health, in operations.
A carbon case for indigenous slate
UK slate can offer clear embodied carbon advantages.
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.